Background/Project Summary
New Zealand firm Tomlinson and Carruthers Surveyors Ltd has been in operation
for over 55 years. It operates in the Wairarapa region (approximately 100km
north-east of Wellington) and covers a radius of about 150km around its
Masterton office.
Traditionally, cadastral surveying has been the firm’s main focus but in recent
times Tomlinson and Carruthers has branched out into more extensive roading,
engineering and subdivision designs.
Surveyor Derek Roberts said, “I think the engineering design work we’re now
doing is increasing due to a buoyant and expanding industry, combined with new
staff and a new curriculum in the New Zealand Surveying degree that has covered
changing technology such as using 12d Model and GPS.”
“For example, 12d Model was used extensively on a recent project in the northern
end of Masterton, near a big roundabout on the way out of town. The land
concerned is known as ‘the horseshoe’, which was part of a significant local car
park.”
The Challenge
“The project started as a straightforward two-lot subdivision to provide a
council-owned car park with the balance remaining in private ownership. On
closer inspection it was found that a larger than normal percentage of the land
was actually being utilised as road. To formalise the situation these areas were
vested as road in the ownership of the Local District Council. The back of the
footpath was used to define the inside lot boundary with the outside being the
existing Certificate of Title boundary (road carriageway). In conjunction with
this, to the south-west there is part of a river with an open stream flowing
through the area. The stream actually forms a natural boundary which we picked
up to be compared with the underlying data in preparation for a future project.”
The Solution
“We did absolutely everything in 12d for this job, including creating all
cadastral data, design, CAD and plotting. We started by creating our scheme plan
(plan of proposal) in 12d which was plotted out and used as part of the
application, and then survey pre-calcs were completed within 12d before visiting
the site. This information was uploaded into the GPS unit directly from 12d, so
when on site we were able to walk directly onto these marks via coordinates
rather than having to use conventional methods. This in particular has meant a
huge saving in time and also given us a different approach to the majority of
our jobs.”
“The information gathered by GPS and also conventional instruments was then
downloaded into 12d Model. This data was used to form the basis of the 12d
traverse spread sheets through which the majority of the linework for the title
and survey plans was prepared and submitted on A2 litho paper. As this project
was done using GPS, we also had to use the transformation functions to work out
and apply the appropriate scale factors. Using GPS combined with 12d Model’s
interface for processing pre- and post-data has probably halved the time
required on site. A project of this nature would take approximately two weeks’
worth of work spread over the different stages, including about three days in
the field and five days’ worth of calculations and drafting. This is phenomenal
compared with the time it would have taken using conventional methods!”
“For Tomlinson and Carruthers, the major benefits of using 12d on this and
similar projects have come from the 12d traverse spread sheet – in particular
the way it does all the line work, point symbols and annotation of the plan all
at once. This has the advantage over other software because 12d is able to
calculate and annotate the true information rather than just the projected
information.”
The Result
“Once the information is in the 12d traverse spread sheet, the drafting is done
automatically. This means the potential for human error – which occurs mainly
with reading and writing at the different stages – is kept to a minimum while
the whole process is simplified and sped up. We are finding that using 12d Model
in conjunction with GPS is saving us around 30-50% of our time spent on this and
other projects. 12d’s ability to reduce errors has served us well, particularly
with the use of GPS and electronic data recorders. Though you can never beat
independent checks, the Traverse Spread Sheet Drafting has removed one of the
more difficult areas to police.”
“Luckily, we have found that the training curve for 12d is very small, even for
those with minimal CAD experience. For new users of 12d, probably half the
learning time has been spent gaining an understanding of survey calculation
methods rather than of 12d itself. Ease of learning was particularly facilitated
by the ability to set up default files and screens to standardise procedures
throughout the office and the whole firm.”
“Being a former SDR Map user, I found the 12d traverse spread sheet very
appealing and easy to use overall. 12d has really revolutionised our methods and
our approach to the majority of our projects!”
Download this Case Study as a PDF
HERE