Khalifa Ports and Industrial Zone
Project Summary
Khalifa Port and Industrial Zone Abu Dhabi is one of the world’s largest
greenfield development projects as well as one of the world’s largest combined
port and industrial zone developments. It is an integral part of Abu Dhabi’s
vision of sustainable economic growth in the United Arab Emirates (UAE). The
industrial zone is located almost equidistant to Abu Dhabi and Dubai, with
extended frontage along the E11 Highway connecting the two cities.
Habtoor Leighton Group was proud to secure
the project. Scope of work includes the onshore civil and building package for
the Khalifa Port and Industrial Zone. As a design and construction project, the
works included around 40 buildings ranging from single guard houses to the
80,0000 square metre central facilities, to civil engineering infrastructure
works such as 18km of 4 -and 6-lane expressway, 38 RCC culverts, 2 interchanges
with entry and exit ramps, 2 railway bridges, and 11kV/33kV networking. Other
utilities such as combined waste water, potable water, groundwater, stormwater,
process water and services are also included, as are associated infrastructure
works consisting of a series of road networks, bridges, utility installations,
containment structures, reinforced earth embankments, patrol roads, an exterior
maintenance system, MEP works, building detailing, signage, hard and soft
landscaping, and maintenance.
The Challenge
This complex project involved design issues such as road top level clashes with
existing utilities, bridges, culverts, and the deck top level. Most of the road
profiles the team used were revised as per site condition. At the project’s
outset, it seemed there would not even be enough time for them to design
profiles and work out these issues before the milestone.
The Solution
With the help of 12d Model software, though, the Leighton team did achieve
success in this project.
They raised the levels on the profile as
necessary, edited super alignments by string, and changed the vertical
intersection points from the vertical IP properties. They also input all the
data such as IP chainages, vertical curve length, and ‘click to set’, by which
12d Model automatically regenerated the vertical profile and automatically set
the k values and radius as required, giving the ability to change the profile of
roads as per the control line.
Next, they edited their design models and
retriangulates TINs as per the new controls, then uploaded to the millimetre GPS
in asphalt paver, by which they were able to smoothly pave asphalt with the
required thickness above the concrete deck.
In addition to assisting design, 12d Model
helped the team to minimise their required survey crew, as they did not need to
fix any Line/Levels on the pavement work. Once they created models, they were
able to upload these to the machines (graders, bull dozers, etc.) so that a
single operator could finished the grading work both quantitatively and
qualitatively.
12d Model also helped the
team to prepare conformance reports, plotting the topographic survey in a short
time and with attractive presentation.
The Result
The Leighton team found 12d Model to be a very efficient and useful software
product to help them save a great deal of money by reducing manpower and time,
and helping them finish their project ahead of schedule.
Download this Case Study as a PDF
HERE