Ballarat Airport - Infrastructure Upgrade
Project Summary
The Ballarat Airport Infrastructure Upgrade Project involved hydraulic
analysis to resolve historical overland flooding of airport operations. This
study formed the basis of the civil design response, with a view to providing
protection during a 1in100 Year storm event. Civil design involved liaison with
Airport planning authorities and agreement on the pavement make-up for both
aircraft and vehicles. It was critical to create a new hardstand in a previously
flood-prone part of the Airport, and as a consequence ‘value add’ to the overall
Airport facility.
Background
The Airport is home to several flight training schools and is also used for such
things as fire and medical services, aerial agriculture, charter services,
recreational flying, aircraft maintenance. The Infrastructure Upgrade project
consisted of detail design and costing of the following elements:
-
450m of Access Road
-
2 Road Intersections
-
1 Court head
-
850 m2 of Carpark
-
750 m2 of Building Pad
-
1.6 ha of Apron and taxiway
-
1.3 ha of Retarding Basin
-
700m of Floodway Main Channel
-
Construction of embankment at the perimeter of retarding basin and the main
channel to accommodate
- 200mm
freeboard
- 516m of Permanent Swale
- 320m of Pipe Drain
Challenges
Solutions
The main channel and the access road were designed first, then separate TINs
created. After that, modifiers such as fixed fall to strings, width to strings,
fixed fall to TINs, etc. were used from Access Road to Main Channel and
vice versa, to model the interface. This aspect was also challenging, in that
both surfaces and strings (Access Road and Main Channel) were used against each
other to create an ‘optimised’ model.
A TIN
was created with the design fixed RL. The pilot channel was modelled. Modifiers
were used to interface with fixed RL TIN. Because of curvilinear pilot channel
geometry, strings were intersected at the concave side of the curve. 12d Model
has the flexibility to perform tasks automatically and in circumstances as
described above, strings can be drawn manually at desired interval, grades,
height, etc.
Results
Detailed design of all the above elements using 12d documentation, and
finalising schedule of quantities within a 4-week program, was achieved. The use
of 12d Model software enabled all deliverables to be met with accuracy. Another
remarkable aspect was the ability to provide a 3D model to the civil contractor
and the Airport authority and not have a single construction issue arise.
Download this Case Study as a PDF
HERE