Project Summary
In early 2001, Hornsby Shire Council took ownership of Hornsby Quarry
following its closure by Boral, creating a need to decide what to do with the
space. In 2014, the NSW State Government announced the construction of the M1
tunnel extension (NorthConnex) linking the M1 to the M2, and this provided
Council with an opportunity to fill the quarry with clean material and create a
recreational facility.
The Challenge
The overall challenge of what to do with a 3.5 million cubic metre hole in the
ground was not insignificant. Many years ago, this could have been turned into a
landfill or tip site, but with today’s environmental responsibilities this was
obviously not an option.
A design solution
had to be undertaken, and the volume of material required to fill the quarry
excavation to a suitable level had to be investigated. There were many
geotechnical, environmental and engineering issues involved - e.g. slope
instability, preservation of the geological features, areas of sensitive
vegetation, and providing suitable access to the finished surfaces.
Preliminary conceptual designs were undertaken, with the constraints taken into
consideration and early volume calculations performed, but during the early
design stages the volume of material likely to be provided from the tunnel
excavation was not known. One of the biggest design problems was providing a
finished design level that would not only make the area functional and retain
some of the existing topography (too low and it would still look like a quarry
hole and have little functionality, too high and the area would look like a
billiard table) but also suit the volume of material likely to be provided from
the tunnel excavation.
According to Roads
and Maritime Services NSW (RMS), the construction of NorthConnex produced around
2.6 million cubic metres of spoil. Hornsby Quarry was one of six sites
identified in the NorthConnex Environmental Impact Statement as having the
necessary capacity to receive spoil material generated by the project.
Once the NorthConnex team was able to provide Council with the estimate of the
volume from the tunnel, a considerable shortfall was found, so designs had to be
reworked or additional material sourced from the surrounding area through
possible reshaping of the quarry walls or lowering the Old Man’s Valley area.
Again, designs were reworked and volume calculations were undertaken to try and
achieve a suitable balanced result.
The
quarry was filled by NorthConnex during 2018 (see attached photo). The fill
material was spread and compacted to a level finish. Another detailed survey of
the site was undertaken, and with the use of 12d Model software, volumes were
calculated to determine the total volume of fill that was imported into the
site. The accuracy of this was very important as the funding agreement between
Council, RMS, and NorthConnex relied upon the quantity of fill placed in the
quarry (measured in cubic metres).
The Solution
Through using 12d Model, numerous designs and finished levels were able to be
explored and tested to provide the most suitable and balanced solution.
Information was able to be extracted and documented in reports to Council.
12d Model’s visualisations/flyovers/drive-throughs made communicating designs to
non-technical people, and to Council, a breeze. These were prepared and
presented Council at workshops to assist in explaining design options and give a
better understanding of issues involved as well as showing them what the final
design may look like.
The Result
A functional recreational facility of great benefit to the greater Hornsby
community was created. Transport for NSW managed the beneficial reuse of more
than one million cubic metres of spoil from NorthConnex at Hornsby Quarry - an
environmentally sustainable use for the spoil. 12d Model was integral to many
stages of this complicated process.
Download this Case Study as a PDF
HERE